Bus franchising - the procurement route ahead

Introduction

We continue this series of guides to Bus Franchising and the Procurement Act 2023 with this second guide. We cover the decision-making process that a franchise authority is expected to follow leading up to formal initiation of the procurement process and then the two routes to contract award that are typically adopted - each of which leads to selection of a successful bidder.

Commencement of the procurement phase sees the end of the preliminary engagement period. If you have not read our first guide covering that phase you can find it here.

What you will find in this guide:

Initial considerations for the authority – what it needs to get right throughout the process

Clearly, the franchising authority must have:

  • established a good understanding of the scope of the procurement exercise. This will, in turn reflect the overall geographic area that is included in the franchise scheme and it will be ready to develop and provide to bidders a specification of the services that it will be procuring (typically described as a “statement of requirements”)
  • a full understanding of the procurement rules as they will apply to the procurement. These are to be found in the Procurement Act 2023 (the “PA 2023”) and regulations made under that Act of Parliament. The Direct Award provisions of the amended Public Service Obligations in Transport Regulations amended by the Bus Services Act 2025 will also in future require to be taken into account
  • an appreciation of the DfT Guidance for bus franchising – the latest edition published on January 29th 2026

The franchising authority will most likely have prepared the operator market for the procurement having undertaken a preliminary market engagement exercise.

The franchising authority will also have considered the professional support that it requires in order to successfully manage what will prove to be a complex procurement exercise. It should also have ensured that anything not yet certain but which has to be in place for the procurement to be successful is being taken forward on a basis that is consistent with the procurement timeline. An example of this in bus franchising is the ability to give possession of depots where this is essential to ensuring that service costs are as optimal as possible. Early experience suggests that Authorities may not have that aspect in place when the procurement commences – meaning that certain aspects of the Statement of Requirements in relation to the depot location, size, availability and leasing or asset ownership and TUPE costs may not yet be clear for Operators to have sufficient information to price their tenders reliably.

The franchising authority must also ensure that its actions at all stages in the process uphold four important principles set out at s12{1} of the PA2023:

  • delivering value for money
  • maximising public benefit
  • sharing information for the purpose of allowing suppliers and others to understand the authority’s procurement policies and decisions
  • acting and being seen to act, with integrity

In addition, the franchising authority will be expected to have regard to the National Procurement Policy Statement published by the UK government when conducting the procurement – in essence, to look to achieve outcomes from the procurement that support government’s objectives such as the growth agenda.

Operators engaged in a procurement exercise will want to keep in mind, in particular, the last two of the principles. Straying from the straight and narrow in the way the procurement is organised and taken forward does not automatically create grounds for challenge but deviations or outright disregard can provide grounds for remedy on the part of bidders and crucially, potentially delay to the procurement process, award of contracts and franchised services beginning.

Many bus franchise procurements will include, amongst bidders, at least one incumbent bidder – already operating bus services in the area subject to franchising. This adds an additional layer of complexity to the Authority’s responsibilities – we will be covering this issue in detail in a future guide.

A further important issue for the franchising authority is the process involved in inviting interest in the procurement, avoiding taking forward candidates (including their key subcontractors) that are on the list of excluded suppliers, considering the appropriateness of taking into procurement any party that is excludable from the process and then ensuring that a fair and appropriate set of criteria are developed and published explaining how particular operators will be selected to enter into the full procurement process.


[1] This could lead to contentious issues arising subsequently as it could involve revision to risk allocation from the position initially represented or involve some other material amendment to the service requirements.

Why the authority will be awarding contracts as a utility

Why the authority will be awarding contracts as a utility

The franchising authority must give thought to the nature of the contract that it plans to award. Given that the franchising provisions of the Transport Act 2000, when activated, prevent operators providing services within the franchise area (save under permit or where the type of service operated is excluded from the franchising scheme) there are, effectively, exclusive rights available to the franchising authority which in exercise of these rights  permits the franchise authority to award contracts that enable the franchising authority to take advantage of these exclusive rights.

This position is confirmed by paragraph 4 of Schedule 4 to the PA2023 which states:

An activity is a utility activity if it relates to the provision or operation of a network for the provision of a service to the general public for transport, whether by rail, tram, bus or other means.

But the contract to be awarded will not of itself have utility status – so what does that mean in practice? 

Contracts awarded by the franchising authority will not have utility status when competitively tendered – s6(4) of the PA2003.

The franchising authority will be considered to have, by law, exclusive rights in relation to the award of contracts covering a bus network. However, the authority only has that status in order that contracts awarded by the franchising authority and taking advantage of the exclusive rights are treated correctly under procurement rules. This rather limited status means that a raft of other provisions applicable to utilities – such as water and energy supply companies – do not become relevant in consequence of a competitively tendered contract being awarded to operate any part of a bus network.

The choice of procurement routes typically adopted

A key benefit of the procurement reforms implemented in the United Kingdom is a simplification of the procurement routes that are available to be followed by the franchising authority. These now comprise:

When the franchising authority can exclude an operator from the opportunity to participate

An important responsibility on the part of a franchising authority is to ensure that it takes through into the procurement process only operators who satisfy rules relating to eligibility to take part in the process.

In the first example of its kind, West Yorkshire Combined Authority has elected not to charge fees for participation in the bus franchising dynamic market established in October 2025.

The timescales that must be provided for in order to allow bidders appropriate time to respond

A number of stages in the process leading to a contract award are governed by minimum timescales that the Authority is required to comply with. Failure to comply can be challenged.

Importantly, the franchising authority should not default to the minimum periods at any stage in the process. The PA2023 requires the franchising authority to actively consider the circumstances surrounding the time period that it will set. Specifically it must take into account as appropriate:

  • The nature and complexity of the contract being awarded
  • Requirements for site visits, physical inspections and other practical steps
  • Any need for sub-contracting
  • If the scope of the tender or any requirements to feature in the contract awarded have been modified there should be taken into account the nature and complexity of any modification of the tender notice or any associated tender documents
  • The importance of avoiding unnecessary delay

Cabinet Office guidance covering the subject of timescales makes an important point in relation to the final issue above. The more complex a procurement is, the greater the risk that the detail to be shared with bidders is just not ready when the procurement starts. Later submission of important information to bidders can inevitably lead to legitimate demands for an extended bid period. 

The Cabinet Office guidance encourages authorities not to commence a procurement process without having all procurement documents ready to be shared with potential operators at that point in time.

A further point emphasised in the Cabinet Office guidance is the importance of reflecting appropriate time periods where SME operators are encouraged to participate in the process. An inappropriately short period of time may deter operators in this class from participating.

Key timescales

Key timescales

Assuming that the franchising authority is pursuing the procurement by forming a dynamic market and then, working through a series of procurements with members of that market, the following are the key timelines.

  • Joining the dynamic market: No specific timeline but the franchising authority should set a date by which an application should be made in order to participate in the first round of bidding opportunities available within the market
  • Participation period where there is no dynamic market: A minimum period of 25 calendar days should be provided for operators to respond to an invitation document
  • At the end of this period the franchising authority is entitled to issue its finalised instructions to submit a tender
  • Tendering period: a minimum of 10 calendar days is required to be provided

A brief introduction to the evaluation process leading to a contract award

Readers experienced in public procurement exercises will appreciate that, previously, public authorities, in evaluating tenders, had the objective of identifying the most economically advantageous tender. The terminology is now contracted and is a reference to the most advantageous tender.

The removal of reference to economic is a reflection of the fact that price (which has previously been treated with particular significance) is just one of many factors that should be evaluated. Each procurement must be based upon its own specific criteria and that economic matters such as price are, in principle, no more significant than other criteria that may be adopted. In a high value procurement such as leading to the award of bus service contracts price will of course be a very significant selection criteria and can still carry the highest level of weighting but for lower value procurement exercises price may be regarded as of less importance.

What has changed is the procedural process for providing tender feedback. There is a requirement on the part of the authority to provide what is now known as an Assessment Summary – a report back to the tenderer on its tender evaluation.

Individual summaries are to be provided to all tenderers specifically – including those that are successful – and should explain why a tender was successful or unsuccessful including enough detail for suppliers to understand the evaluation process as it applied to that candidates bid.

A standstill period still applies with a minimum of 8 working days (previously 10 calendar days) and the assessment summaries must be issued before a contract award notice is published and the standstill period commences.

It can only be hoped that, given the early stage that bus franchising procurement is at, assessment summaries provide meaningful benefit to unsuccessful bidders who will, no doubt, move on to the next opportunity and able to use the feedback to win future bus franchising bids.

The franchising authority should consider carefully the timeline that it develops once evaluation has been completed. Consideration will need to be given to the level of authorisation available to the director responsible for the contract award and whether a report and recommendation must be taken to the franchising authority’s board. 

Only when all procedural steps are in place can notice of the contract award(s) and assessment documentation be issued to tenderers. The 8 working day standstill period can commence immediately but consideration can be given to allowing a period for tenderers to absorb information provided within the assessment documentation and raise legitimate concerns before the timeline for standstill begins.

A final point – equal treatment for all in a bus franchise procurement? Not necessarily!

Sections 12(2) and 12(3) of the PA2003 tell us that equal treatment is not always the mantra for a compliant public procurement process. This is a particularly important issue in the context of bus franchising as operators bidding for local service contracts under the franchising scheme will in many cases be bidding to retain a business interest that they already have.

The PA 2023 makes clear that a franchising authority should consider with care the nature of the parties that are to become tenderers and if there is a difference between the bidders this entitles the franchising authority to treat particular bidders differently. But this is followed with a cautionary statement:

If a contracting authority considers that different treatment is justified in a particular case, the authority must take all reasonable steps to ensure it does not put a supplier at an unfair advantage or disadvantage.

The principle of permitted discrimination is a hugely important challenge for the franchising authority to get right. The integrity of the procurement process is at risk if this issue is not handled correctly. Next in this series will be a guide to the management of incumbent bidders in franchise procurements.

Case study

How West Yorkshire Combined Authority has taken forward the early stages of the  first bus franchise procurement exercise undertaken  within a dynamic market.

West Yorkshire Combined Authority (“WYCA”) formally launched its dynamic market on 18th August 2025 inviting operators to submit applications for membership and setting out the requirements necessary to secure that status.

On 3rd October 2025 a second notice was published confirming the establishment of the market and naming the operators that had been accepted into membership. 

An invitation to tender document was issued to all then participants in the market (according to the lots that each Operator has been accepted into) and set out the following timetable for what is described as Tier A contracts – with three in total to be awarded with peak vehicle requirements ranging from 49 to 119. The following process was proposed:

Stage 1: Conditions of participation: Operators were required to submit responses to a Procurement Specific Questionnaire which set out pass/fail questions to be responded to. Operators passing the requirements of this phase moved on to dialogue phase

Stage 2: Dialogue: Operators passing the Conditions of Participation phase now become tenderers and in a position to submit a tender against WYCA’s request for tenders. A dialogue phase then took place with operators invited to participate in a range of thematic sessions covering matters such as Network and operations, assets, legal and payment mechanism and performance management regime.

Stage 3: Tender: Commencement marked by the issue of final tender documentation followed by submission of tenders, evaluation and contract award.

The specific timetable published was as follows:

Event Date
ITT made available 7 October 2025
Deadline for initial clarification questions (these related to the Procurement Specific Questionnaire) 14 October 2025
Final date for responses to the initial clarification questions 21 October 2025
Deadline for operators to return a completed Procurement Specific Questionnaire 3 November 2025, 12pm
Dialogue stage
Invitations to dialogue published 10 November 2025
Dialogue finishes

10 November 2025

Commentary on the draft Franchise Agreement required by this date

21 November 2025, 12pm

Reissue updated draft Franchise Agreement 5 December 2025
Dialogue finishes 19 December 2025
Tender stage
Invitation to Tender issued 12 January 2026
Deadline for tender clarification questions 13 February 2026
Final date for responses to tender clarification questions 20 February 2026
Tender submission deadline 27 February 2026, 12pm
Completion of evaluation From 1 June 2026
Contract and lease documentation executed 29 June 2026
Service Commencement Date 4 April 2027, 1am

Stay ahead with our upcoming guides

We hope you’ve found this guide to Preliminary Market Engagement and Bus Franchising insightful.

As part of our commitment to supporting the development of bus franchising in the UK, we’re producing a series of guides exploring key aspects of the procurement process. See across for the next few issues.

To be among the first to receive our procurement and bus franchising guides, sign up to our mailing list.

Subscribe to our mailing list
The procurement process and the route to contract award

Coming soon

There are now just two routes to contract award - open and competitive flexible. This guide explains how procurement processes now work.

Engaging in a competitive flexible tender procedure

Coming soon

A Freeths’ guide to making the most of the opportunity.

The content of this page is a summary of the law in force at the date of publication and is not exhaustive, nor does it contain definitive advice. Specialist legal advice should be sought in relation to any queries that may arise.

Get in touch

Contact us today

Whatever your legal needs, our wide ranging expertise is here to support you and your business, so let’s start your legal journey today and get you in touch with the right lawyer to get you started.

Telephone

Get in touch

For general enquiries, please complete this form and we will direct your message to the most appropriate person.